At 8:55 am this morning, the piling team of Danny, Jayden and Zak made their way down to Over Alderley, on the outskirts of Macclesfield, to complete the piling for the foundation of a brand-new farmhouse.

It required 48x 168mm piles in total, and the team managed to drive an average of 9 piles per day with the Grundomat for a turnaround time of 5 days or just one working week.

We’re piling and caging this one, so check back to see the next stage of the project.